191 GW of Planned Data Center Capacity Faces New Political Risk
Orennia counts 191 GW of planned data center capacity at risk, concentrated in Texas, Ohio and Georgia. ERCOT could see solar revenue fall 38% if 20% of demand evaporates.

Clearance
- 191 GW of planned data center capacity faces new risk, concentrated in Texas, Ohio and Georgia (Orennia).
- A 20% ERCOT demand shortfall would cut solar wholesale revenue 38% and wind 37%; PJM delays cut battery spreads 16% through 2030.
- AEP Ohio's July 2025 tariff requires loads above 25 MW to pay for 85% of capacity up to 12 years; the pipeline fell from 30+ GW to about 13.
- Texas Governor Abbott lost reelection to Gina Hinojosa after pausing data center interconnections over the summer.
- Nearly all 46 municipal ballot measures tracked by Bloomberg on data centers resulted in restrictions or bans.
An estimated 191 GW of planned data center capacity now faces new risk after the midterms, with exposure concentrated in Texas, Ohio and Georgia. That figure comes from energy analytics firm Orennia, which shared its report with Utility Dive. Nearly all of the 46 municipal ballot measures tracked by Bloomberg on data center development ended in restrictions, moratoriums or bans. Utilities could be left holding the bill for infrastructure committed against loads that never arrive.
The political shift cuts across party lines. Incoming Democratic governors in three big markets campaigned on pausing or restricting construction, and Democratic gains in the midterms add pressure on earlier-stage investments.
What happens to utility cost recovery?
The core mechanism is cost allocation. Utilities build transmission, interconnection capacity and generation against projected load. If that load is delayed, downsized or canceled, the spending stays on the books and regulators must decide who pays.
Investors are already repricing that risk. "From a financing perspective, prolonged uncertainty will increase the cost of capital, reduce available leverage and make investors more hesitant to commit significant development dollars before power is secured," said Andrejka Bernatova, managing partner of investment firm Dynamix Capital Partners.
Bernatova said interconnection, permitting and financing form one execution question: whether a team can deliver reliable power to a site. A customer commitment or a large announced capacity number does not answer that by itself. She expects capital to favor markets with certainty on power availability and timelines, which could erode Texas' recent competitive advantage.
Texas carries the largest stake. Governor Greg Abbott, a Republican, paused new data center interconnections over the summer pending an audit of the queue. He then lost his reelection bid to Democrat Gina Hinojosa, who has pledged to keep pressure on the industry after taking office next year. Texas holds nearly half of U.S. pre-construction development, so a statewide approval freeze would hit the national buildout hard.
Takeaway: the money question is not whether data centers get built, but who eats stranded infrastructure when they do not.
How hard does the generation revenue hit land?
Orennia modeled two slowdown scenarios with concrete numbers:
- ERCOT: If 20% of projected data center demand fails to materialize, average wholesale revenue falls 38% for solar and 37% for wind. Implied heat rates (the economics of gas-fired generation relative to fuel cost) decline 39%. Two-hour battery storage arbitrage spreads (the price gap batteries profit from) fall below new-build break-even.
- PJM: Delaying half the planned buildout by two years cuts four-hour battery arbitrage spreads 16% and lowers solar, wind and heat-rate capture prices roughly 12% through 2030.
Existing safeguards may not hold. Louisa Eberle, principal at the Regulatory Assistance Project, said existing tariffs and regulatory frameworks "likely won't fully protect customers because they were designed for a different century." She called for reforms to utility business practices to turn the data center surge into updated infrastructure, cleaner energy and a better deal for average customers.
Are large-load tariffs doing the job?
Tariff design is the frontline defense. AEP Ohio's large-load tariff, approved in July 2025, requires new data centers above 25 MW to pay for at least 85% of requested capacity for up to 12 years, with exit fees and financial guarantees. The utility's data center pipeline fell from more than 30 GW to about 13.
Stephen Rose, CEO of infrastructure software provider Render Networks, expects a "pause and necessary shakeout." His read on who takes the hit:
- Fully permitted projects with real capital keep moving.
- Speculative developers land-banking without firm power stall out.
- Contractors who staffed up for projects that will not break ground absorb the damage.
Rose pointed to Louisiana's delayed BEAD broadband program in 2025 as a template. "When timelines stalled, the hit didn't land on big tech balance sheets. It landed on local drilling, civil and fiber contractors," he said. "A data center slowdown hits the same people first, and Texas risks the same fallout."
Will permitting fights just move the projects?
Andy Roehr, managing director at Baker Tilly's energy and infrastructure practice, sees redirection, not cancellation. A developer typically evaluates three to five sites at once, so hostile permitting in one jurisdiction means delay or redirection.
Moratoria may even hand leverage to developers. "These moratoria are creating a developer's market since they have the assets, tax revenues and jobs that communities want or need," Roehr said. Some developers will accept less optimal sites where the price point and time-to-market work and the regulatory climate is less hostile.
Grid utilization is also rising as a policy priority. Virginia Governor Abigail Spanberger signed legislation in April requiring Dominion Energy and Appalachian Power to report how effectively they use existing infrastructure, with the State Corporation Commission empowered to set improvement targets.
"Winning candidates who emphasized lowering electricity prices are already looking for ways to deliver on their promises quickly," said Richard Caperton, vice president of policy at SPAN, a smart electrical panel maker. He expects utilization policies to be ratified and implemented in early 2027, with effects varying by state.
The wildcard is federal permitting reform. The Bipartisan American Affordability and Jobs Act advanced in the Senate last week but faces a difficult path after the midterms. Roehr called it an "all of the above" bill, meaningful for solar, nuclear and natural gas alike. What the industry needs most, he said, is stability: "These are 20-, 40-, even 60-year investments, and if the environment keeps whipsawing then jobs don't appear, tax payments don't appear and capital moves on — there will be no winners."
via Utility Dive (Source)