DOE Offers $2.8B Loan for 1.8-GW Wyoming Intertie Grid Link
DOE's $2.8B conditional loan would finance 80% of Grid United's 1,800-MW, 106-mile Wyoming Intertie, more than doubling the 1,320 MW linking the Eastern and Western grids.

Clearance
- DOE offered up to $2.8 billion in conditional financing for Wyoming Intertie on Nov. 17.
- The 1,800-MW, 106-mile line would more than double existing East-West transfer capacity of 1,320 MW.
- The loan covers 80% of construction costs over 30 years and could be assigned to capacity-buying utilities.
- Construction could begin as early as 2030, with commercial operation projected for 2032 or 2033.
- Grid United estimates $500 million-plus in ratepayer savings versus private financing.
The U.S. Department of Energy has offered up to $2.8 billion in conditional financing for Wyoming Intertie, a proposed 106-mile transmission line in southeastern Wyoming rated at up to 1,800 MW. The line could more than double the 1,320 MW of transfer capacity that currently exists between the Eastern and Western Interconnections, the nation's two largest synchronous grids.
The DOE's Office of Energy Dominance Financing announced the conditional commitment on Nov. 17. Houston-based independent transmission developer Grid United is building the project, which would link the Southwest Power Pool and Western Electricity Coordinating Council regions. The loan could cover 80 percent of construction costs over a 30-year term, and the DOE could assign it to utilities that acquire capacity on the line. The takeaway: federal money would carry most of the project, before a single customer is signed.
What does the money cover?
Grid United's October financing fact sheet sets the terms:
- Loan covers 80% of construction costs over a 30-year term including construction.
- The $2.8 billion excludes interest during construction.
- Disbursements begin only after notice to proceed and construction start.
Grid United estimates the lower federal borrowing rate would save ratepayers more than $500 million compared with private market financing. The DOE estimates the line could yield up to $39 billion in electricity cost savings across 17 states in the WECC and SPP regions, though the department did not detail its methodology. The DOE said the commitment advances President Donald Trump's executive order "Strengthening the Reliability and Security of the U.S. Electric Grid" and builds on September selections under the SPARK program (Speed to Power through Accelerated Reconductoring and other Key Advanced Transmission Technology Upgrades).
How would the interconnection work?
The two interconnections run as separate asynchronous AC systems. They cannot exchange power over conventional AC ties. Seven existing back-to-back HVDC converter facilities (facilities that convert AC to DC and back to AC at one site) enable transfers, with individual ratings of 130 MW to 210 MW across Montana, South Dakota, Nebraska, Colorado and New Mexico. Five date from 1977 to 1988 and use older line-commutated converter technology.
Wyoming Intertie would run from the existing Aeolus substation near Medicine Bow to a proposed HVDC back-to-back converter station near the Laramie River Station outside Wheatland, crossing Carbon, Albany and Platte counties. Documents indicate the converter station would use voltage source converter technology, which Grid United says provides rapid bidirectional power flow control, voltage regulation and black-start support for the neighboring system after a major outage.
"As a networked grid infrastructure asset, Wyoming Intertie will not directly connect to any specific generation or demand source," the company notes in its project materials. The line would carry power from any generation technology in either direction, letting operators tap surplus in one grid during shortages in the other.
What stands between commitment and construction?
The financing arrives early in development. Grid United has not publicly identified capacity customers. Conditions for financial close include commercial capacity contracts, full right-of-way acquisition, federal, state and local permits, and compliance with federal program requirements. The DOE also requires technical, legal, environmental and financial conditions before definitive agreements.
The timeline:
- Field surveys began in 2023; right-of-way option acquisition began in 2024.
- The project entered the federal CITAP permitting process in 2025.
- State and county permitting runs concurrently in 2027 and 2028.
- A federal record of decision and notice to proceed are expected in 2029.
- Construction could begin as early as 2030; commercial operation in 2032 or 2033.
The route crosses federal land requiring NEPA review. The state requires an Industrial Siting Certificate from the Wyoming Department of Environmental Quality. Carbon and Platte counties require conditional use permits; Albany County currently does not. The project's community investment program, run with the Wyoming Community Foundation, had awarded $1.2 million to 73 organizations as of October 2026.
Where does this fit Grid United's portfolio?
Grid United is developing five projects. The 3,000-MW, 420-mile North Plains Connector between Montana and North Dakota received roughly $620 million of a $695 million GRIP award finalized Oct. 22, 2026. The 1,800-MW Three Corners Connector between Pueblo, Colorado, and Guymon, Oklahoma, seeks up to $250 million under SPARK, with a final environmental impact statement still pending. Southline, co-developed with Black Forest Partners, holds DOE capacity contracts under the $2.5 billion Transmission Facilitation Program. Three projects with VSC technology total 6,600 MW, five times existing East-West capability.
EDF, formerly the Loan Programs Office, holds more than $289 billion in loan authority. It closed a $3.26 billion loan to AEP Texas in July 2026 and a $5.1 billion package for Alliant Energy in October. Unlike those regulated-utility deals, the Wyoming Intertie commitment precedes commercial contracting, and loan assignment to capacity buyers could sweeten those agreements before construction. In plain terms: the money is real, but the customers are not yet.
via energy.gov (Original)
More from Priya Raman
Show full bio
Senior reporter covering people, launches and day-to-day practice in Wiring News is the daily trade press for at Wiring News.
10 articles
Alternates · Related articles
191 GW of Planned Data Center Capacity Faces New Political Risk
Enel Buys 317 MWdc South Carolina Solar Portfolio From energyRe
EIA: Commercial Load Overtakes Residential in 2026
Exus Locks In $345 Million to Build Out 6 GW U.S. Renewables Pipeline
411 Grid Modernization Actions Shift Focus to Existing Capacity