Industrial Electrical3 min read637 words

LS Electric Lands $93.83M Switchgear Order for US AI Data Center Expansion

LS Electric won a $93.83 million (130 billion won) contract to supply 38kV and low-voltage switchgear for a US big tech hyperscale AI data center expansion, a repeat order built on delivery speed.

South Korea's LS Electric Wins 130 Billion Won Order to Supply Switchgear for US Big Tech AI Data Center - BigGo Finance
South Korea's LS Electric Wins 130 Billion Won Order to Supply Switchgear for US Big Tech AI Data Center - BigGo FinanceAkela999 / pixabay

Clearance

  • LS Electric signed a $93.83 million (about 130 billion won) switchgear contract, disclosed in a regulatory filing on the 16th.
  • The order covers 38kV high-voltage and low-voltage switchgear for a US big tech hyperscale data center expansion.
  • Production spans Cheongju, South Korea; Utah; and the Bastrop Campus in Texas.
  • LS Electric operates a commercialized DC distribution 'DC Factory' in Cheonan and demos SST, SSCB and ESS tech.
  • The deal is a repeat order following a recent long-term supply agreement with another big tech customer.

LS Electric (KRX: 010120) has signed a contract worth approximately $93.83 million, about 130 billion won, to supply power distribution equipment for the expansion of a US hyperscale AI data center. The South Korean manufacturer disclosed the deal in a regulatory filing on the 16th.

The contract covers 38kV high-voltage switchgear and low-voltage switchgear — the core gear in a data center's power chain. Switchgear steps down incoming high-voltage utility power and distributes it to server racks, cooling systems and other loads. Engineers classify it as the component that ultimately determines a facility's power reliability.

Who is the customer?

The buyer is a global big tech company based in the United States, which LS Electric did not name. The order is a repeat: LS Electric worked on the same company's large data center project from its early stages, and this new volume covers the expansion phase.

A company official said: "This order is the result of our power equipment quality competitiveness and our project execution capabilities in the North American market being recognized once again."

Why did LS Electric win the volume?

Delivery speed carried as much weight as product specs. As AI buildouts accelerate, "time to power" — the elapsed time between a data center receiving power and actually beginning operations — has become a variable that decides business competitiveness. Owners now screen suppliers on schedule performance, not just quality certifications.

"From the early stages of the project, we have been winning orders by meeting not only quality requirements but also the delivery timelines data centers demand," the company stated.

Where will the gear be built?

LS Electric splits production across three bases on two continents:

  • A smart factory in Cheongju, South Korea
  • LS Electric Utah, in the US state of Utah
  • The Bastrop Campus in Texas

The company says this footprint gives it the supply capacity to hit North American customers' order schedules.

What comes next: DC distribution

LS Electric plans to use the contract as a springboard into next-generation power distribution. Data center power grids today run mainly on alternating current (AC). Direct current (DC) distribution, which cuts power conversion losses, is drawing attention as the successor technology.

The company already operates a "DC Factory" at its Cheonan facility, where it has commercialized DC distribution for manufacturing plants. It is also running demonstrations in next-generation grid and data center environments using:

  • Solid-state transformers (SST)
  • Solid-state circuit breakers (SSCB)
  • Energy storage systems (ESS)

If DC distribution reaches full commercialization, technology competition among suppliers over data center power efficiency is expected to intensify.

A pattern, not a one-off

The order extends a run of North American wins. "Having demonstrated a solid order flow by signing a long-term supply agreement with another big tech company recently, we will continue to expand our business by providing solutions tailored to big tech customers' needs," a company official said.

The market reads the deal as a marker of LS Electric's standing in North America's power equipment order race. With AI data center investment continuing, orders for switchgear and transformers keep climbing, and the contract confirms a pattern: get in at the early project stage, and follow-on expansion volumes follow.

Contract at a glance

Item Details
Contract value ~$93.83 million (~130 billion won)
Supplied items 38kV high-voltage switchgear, low-voltage switchgear
Customer Global big tech company (US), unnamed
Project Expansion of an existing hyperscale data center
Production bases Cheongju smart factory, Utah, Texas (Bastrop)

The dollar figure comes from the company's disclosure; the won equivalent is its own conversion. Deliveries will run sequentially under the contract terms.

For contractors, the takeaway is straightforward: hyperscale owners are rewarding suppliers who can compress time-to-power, and that pressure will reach the electrical trades building these sites.

via Google News · Switchgear & Industrial Power (Source)

Share this article:

More from Amara Osei

Amara Osei

Show full bio

Staff writer covering companies, deals and strategy in Wiring News is the daily trade press for at Wiring News.

10 articles

Alternates · Related articles

  1. LS Electric lands $93.83m switchgear order for hyperscale AI data center

  2. LS ELECTRIC Lands $93.83M Switchgear Order for US AI Data Center

  3. LS Electric Lands $93.83M US Data Center Switchgear Order

  4. Mitsubishi Electric Puts $259.5M Into U.S. Plants

  5. EIA: Commercial Load Overtakes Residential in 2026

« Previous legNext leg »