NRC Issues First HTGR Construction Permit Since 1968 for Dow's Long Mott

The NRC's Nov. 9 permit authorizes four 80-MWe Xe-100 pebble-bed reactors for Dow's Seadrift complex — the first HTGR construction permit since Fort St. Vrain in 1968, with a 2027 investment decision still pending.

Landmark NRC Construction Permit Ushers in Next Phase for Dow’s Xe-100 HTGR Nuclear Project
Landmark NRC Construction Permit Ushers in Next Phase for Dow’s Xe-100 HTGR Nuclear ProjectdistelAPPArath / pixabay

Clearance

  • NRC issued the first HTGR construction permit since September 1968 on Nov. 9, 2027 permitting four Xe-100 reactors totaling 800 MWth / 320 MWe.
  • Dow expects a preliminary investment decision in 2027; the permit sets Dec. 31, 2033 as the latest construction completion date.
  • Calculated peak fuel temperature of 1,885C with uncertainties exceeds typical TRISO limits; the preliminary 30-day dose of 14.4 rem stays below the 25-rem criterion.
  • The X-energy ARDP award rises to $2.15 billion, with $618 million reimbursed by DOE through September 2026.
  • A NextEra Energy Resources subsidiary will operate the plant; TX-1 in Oak Ridge holds the first Category II HALEU fabrication license, capacity 700,000 pebbles per year.

The Nuclear Regulatory Commission on Nov. 9 issued its first construction permit for a high-temperature gas-cooled reactor in nearly six decades. The permit (CPAR-3) authorizes Long Mott Energy LLC, a wholly owned Dow subsidiary, to build four X-energy Xe-100 reactors at a site in Calhoun County, Texas, that will feed electricity and process steam to Dow's Seadrift chemical complex. A permit is not a promise, and Dow has said as much. Construction funding, final design work and an operating license all remain ahead.

The facility will comprise four helium-cooled, graphite-moderated pebble-bed reactors, each rated at 200 MW thermal (MWth) and 80 MW electrical, for 800 MWth and 320 MWe aggregate. That thermal figure nearly matches Fort St. Vrain, the 842-MWth prismatic-block HTGR authorized in September 1968 and the last of its kind permitted in the United States. Long Mott would distribute that heat across four continuously refueled reactors instead of one.

What does the permit actually authorize?

Under the two-step licensing process in 10 CFR Part 50, the NRC may authorize construction before all safety questions are resolved, provided the applicant runs an R&D program designed to close them out first. Long Mott Energy did not seek individual design approvals under 10 CFR 50.35(b) and must substantiate the final design in a separate operating license application.

The numbers that matter to the review:

  • The NRC's 852-page final safety evaluation, issued Oct. 30, and an Oct. 16 Advisory Committee on Reactor Safeguards (ACRS) letter form the technical basis. The ACRS letter stated the review "supports issuance of the construction permit."
  • For a depressurized loss-of-forced-cooling event, the applicant calculated a nominal peak fuel temperature of 1,803C, rising to 1,885C with analytical uncertainties. The NRC's confirmatory MELCOR calculation produced 1,788C. The FSER noted these peaks sit "beyond the limits typically associated with TRISO fuel particles." The preliminary radiological analysis still shows a maximum 30-day dose of 14.4 rem at the exclusion area boundary, below the 25-rem regulatory criterion.
  • Each core holds roughly 220,000 spherical fuel elements with TRISO (tristructural isotropic) coated particles. The reactor uses "functional containment" — successive coating layers around each fuel kernel — rather than a pressure-retaining containment structure.
  • The proposed emergency planning zone extends 400 meters, against the roughly 10 miles typical of light-water plants.
  • Site grade is proposed at 31 feet NAVD 88, while calculated storm surge with wave runup reaches 46.49 feet. The permit requires Long Mott to submit flood protection designs before placing safety-significant concrete.

The ACRS cautioned that "both fuel and structural materials are challenged by the peak temperatures predicted under limiting accident conditions," and it flagged fuel performance, functional containment, source term analysis and graphite and metallic component performance as areas requiring significant additional development.

Who builds, who runs, who pays?

Dow has selected a NextEra Energy Resources subsidiary to operate the plant, per Section 2.1.2 of the FSER. The NRC assessed technical qualifications across all three companies: Dow's industrial capital-project experience, X-energy's reactor engineering, and NextEra's operation of seven light-water reactors at four sites. Fluor holds engineering contracts at both Seadrift and Energy Northwest's proposed Cascade facility near Richland, Washington.

X-energy informed investors of an intended increase in its Advanced Reactor Demonstration Program award to $2.15 billion, covering Long Mott and the TRISO-X fuel plant in Tennessee. CFO Daniel Gross said on Nov. 12 the DOE had reimbursed $618 million through September 2026. Under a Feb. 23, 2026 financial support agreement, Dow committed construction funding exceeding half the estimated cost, which supported an NRC exemption from the 10 CFR 50.33(f) financial qualification rule.

What is the schedule?

Dow expects to weigh a preliminary investment decision in 2027, with a final decision authorizing full construction to follow. X-energy targets initial energy delivery in the early 2030s. The permit sets July 1, 2033 as the earliest construction completion date and Dec. 31, 2033 as the latest, expiring then unless extended. CEO Clay Sell said X-energy has begun the operating license application and expects to file roughly two years before commissioning.

The reactor supplies steam at up to 565C, well above light-water reactor output, which suits Seadrift's polyethylene and glycols manufacturing. On fuel, TRISO-X completed the TX-1 facility shell in Oak Ridge in Q3 2026; the NRC granted a 40-year Category II HALEU license in February, and DOE calls it the first commercial-scale HALEU fuel fabrication facility approved in the United States. Capacity is about 700,000 pebbles annually, enough for 11 reactors.

"Regulatory approval is not on the critical path for any of our projects," Sell told analysts. "It really relates more to the supply chain." Alleima will supply steam generator tubing to Doosan Enerbility for the helical coils; Doosan holds reserved capacity for 16 reactor and steam generator vessel sets. X-energy reports $1.8 billion in cash, no debt, and a prospective portfolio of 144 reactors totaling about 11.5 GW.

The verdict for now: a permit in hand, a plant not yet on the slab. Pouring concrete awaits Dow's board, two more years of qualification work, and a hurricane-grade grade-raise design the NRC has not yet seen.

via nrc.gov (Original)

Share this article:

More from Tom Whitfield

Tom Whitfield

Show full bio

News editor covering technology and product news in Wiring News is the daily trade press for at Wiring News.

7 articles

Alternates · Related articles

  1. DOE Offers $2.8B Loan for 1.8-GW Wyoming Intertie Grid Link

  2. Enel Buys 317 MWdc South Carolina Solar Portfolio From energyRe

  3. DTE Seeks Bids for Up to 150 MW of New Michigan Solar

  4. ComEd Pilots 138-kV and 345-kV SF6-Free Breakers as State Phaseouts Loom

  5. U.S. energy storage passes 200 GWh; nine-month installs hit 48.3 GWh

« Previous legNext leg »